Eight spans for BEM side has been completed, now they are about to start for 9th span, and one and last ie 10 span for KSJ side still about to replace which would not consume much time. We can say that in May end or June first,, span work would be finished, then only piping, wiring, signal cables, channel sleepers. and rail work would left to be done..