RDSO, Bridge Testing cum Staff car (saloon) standing at Cuttack railway Station for final inspection of newly constructed five major and seven minor bridges between Cuttack- Barang section
Cuttack- Barang double line was sanctioned in 2003-04 with an estimated cost of Rs 135 crore but the project lingered on. The Rail Vikash Nigam Limited (RVNL), which is implementing the project, finalised the tender in 2006. The 12 km double lining work has gone beyond schedule as contractors left the project mid-way. The delay has only added to the woes of traffic as the section witnesses heavy movement of trains, both passenger and goods. Work for five major and seven minor bridges has been completed while track linking of 11.5 km out of...
more... 12 km has been wrapped up.