Bhai present status between UBL GTL. Hubli se Binkadkatti doubled hai Aur Harlapur se Hospet tak fully doubled. As per CORE targets Hospet Banapur is taken to complete within this FY. So remaining Banapur to Hubli takes time. Also RE works going in intermediate sections like nearby Annigeri so until complete RE /FEDL between Hubli to Guntakal not get commission Eloco for passenger train is not going to be provided. Let's see how and what they do...