Railway Electrification North East Frontier Railway(Project Office : New Jalpaiguri/Group:150 ) : New Jalpaiguri Railway Station.
.
Some Pic of NJP Yard & Outer taken on 27-10-2019. It is evident from these pictures that much of the work related to NJP Yard Electrification is still remaining. But as per the Twitter handle of Core Allahabad, CRS to be done on 1st week of November. I hope only some portion of the NJP will be start functioning and will be limited only for passenger train movement to an extent.
....
more...
Gunjaria TSS to Rangapani TSS work on Electrification is complete and energized(As per CORE Allahabad). Rangapani to NJP(Main Line) some patch work remains. May be they will be able to complete it withing a week.
.
But a full fledged operation may take another 6 Months or more keeping all aspects in consideration.
.
Added some pictures of NJP Outer and Yard for reference.