New bypass line comes to VJA from Rayanapadu to Mustabada.
1st Pic:-As part of the proposed Vijayawada Bypass Rail Line between the Kazipeta-Vijayawada and Vijayawada-Visakhapatnam railway lines, the proposed railway line between Rayanapadu-Mustapad, work on the construction of 2 rail-over-rail bridges and another major bridge has commenced at a cost of Rs 25.04 crore.
2nd Pic:- The construction of various buildings at the VNC Cabin, Quality, and Mustapad will commence at a cost of Rs 6.84 crore with regard to the construction of the proposed Vijayawada Bypass Railway between the Kazipeta-Vijayawada and Vijayawada-Visakhapatnam...
more... Railway lines.
3rd Pic:-
Construction of the proposed Vijayawada Bypass Rail Line between the Kazipeta-Vijayawada and Vijayawada-Visakhapatnam railway lines and the Rayanapadu-Mustapad railway line is expected to start at a cost of Rs 28.34 crore.
PS:- Twitter