#update9
Electrification progress on Moradabad - kashipur - Ramnagar route
Moradabad - Got outer :- Electrification is complete.
Got outer - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring not done.
Kashipur...
more... :- Foundation work complete, Poles erected, brackets placed and wiring not done.
Kashipur outer - Ramnagar outer:- Foundation work complete, Poles erected, brackets placed and wiring not done.
Ramnagar :- Foundation work complete, Poles erected, brackets placed and wiring not done.
This is the progress of electrification on Moradabad - Ramnagar route.
SSP details:-
Pipalsana SSP will completed
Roshanpur SSP completed.
Kashipur SSP work has not started.
Ramnagar SSP work has not started.
Note :-
Wring will start after 5-6 days as now all the poles and brackets are placed on this route. The work is going on in full swing at kashipur junction but they are having less workers. And wiring will be done from start to end in a single day.
2) wiring from Lalkuan side has reached kashipur station just 50 meters before