#ALD_BSB_Electrificationupdate
From ALD to Ganga bridge...poles are placed but not erected
From Ganga bridge side till jhusi..poles are placed and erected as well and in few of them angles as well is placed
From jhusi till few kms before RTR outer poles are erected and angles placed..
From...
more... RTR outer to SDC outer wiring done
At SDC poles are placed..
From SDC outer wiring is in place till RTR outer
A sub station is being developed at HDK and Khachwa road
At RTR holes are in place
After RTR wiring is in place till Nigatpur outer
Nothing at Nigatpur station
After Nigatpur work is going on